CONSTRUCTION OF CONCRETE PEDESTRIAN JETTY, OVIA SOUTH WEST L.G.A. EDO STATE.

BRIEF NOTE: The site location is situated at Nikorogha Community in Ovia South West L.G.A., Edo State.

The project involves the construction of 40 Nos Bored Cased Piles to 15m depth upon which 3.0 m width by 45 m long walkway and 10 by 10m jetty platform will be seated upon and surrounded by 400mm reinforced concrete beam on the water side in Nikorogha Community.

PROJECT STATUS: In Progress – September 2024.


CONSTRUCTION OF CONCRETE PEDESTRIAN JETTY OFUNAMA, OVIA SOUTH WEST L.G.A. EDO STATE.

BRIEF NOTE: The site location is situated at Ofunama Community in Ovia South West L.G.A., Edo State.

The project involves the construction of 60 Nos Bored Cased Piles to 15m depth upon which 3.0 m width by 52 m long walkway and 20 by 8m jetty platform will be seated upon and surrounded by 400mm reinforced concrete beam on the water side in Ofunama Community.

PROJECT STATUS: In Progress – August 2024.

REPAIR OF THE FAILED BRIDGE ABUTEMENTS IN ABUDU COMMUNITY, ORHIONMWON L.G.A. EDO STATE.

BRIEF NOTE: The site location is situated at Abudu Community in Orhionmwon L.G.A., Edo State.

The project involves the use of Gabion Baskets, Renomattress and Hardcores with varying sizes ranging from 200 mm downward to protect the failed sections of the bridge abutements.The hardcores were used to fill the gabion baskets and renomattress, squared and plummed for firmness to create retaining walls around the bridge abutements.

PROJECT STATUS: Completed – August 2024.

ELECTRIFICATION/INSTALLATION OF 300KVA/11KVA/0.415V TRANSFORMER AT IGUOTOR COMMUNITY, OVIA N.E. L.G.A. EDO STATE.

BRIEF NOTE: The site location is situated at Iguotor Community in Ovia North East L.G.A., Edo State

The project involves installation of  No 300kva/11kva/0.415v Transformer and electrification of the the community with additional 5 Nos High Tension (HT) Poles and 27 Nos Low Voltage (LV) Poles.

PROJECT STATUS: Completed – August 2024.


Construction of Concrete Marine Tower and Pedestrian Jetty, Ologbo.

BRIEF NOTE: The site location is situated at Ologbo Community in Ikpoba Okha L.G.A., Edo State

The project involves the construction of 16 Nos Bored Casing Piles to 15m depth upon which 2.5 by 26 m long walkway and 5.0 by 5.0 m jetty high tower will be seated upon and surrounded by 400mm reinforced concrete beam on the waterside on Oriowon River in Ologbo Community.

PROJECT STATUS: Completed – February 2023.

Construction of Concrete Retaining Wall, Block Fence and Drainage at Gelegele Marine Police Post.

BRIEF NOTE: The site location is situated at Gelegele Community in Ovia North East L.G.A., Edo State Nigeria.

The project involves the construction of 0.4m (thickness) by 3m (height) by 51m (length) of reinforced concrete retaining wall, 2.5m wall of block wall on top of the retaining wall and storm water drainage at Gelegele Marine Police Post. Howerevr, the reclaimed area which form part of the compound was concreted with 5mm RBC steel and additional interlocking paved stones was constructed. Other work done was concrete and earth works for slope protection at the section of the building.

PROJECT STATUS: Completed – January 2022.


Construction/Completion of Concrete Pedestrian Jetty, Ologbo.

BRIEF NOTE: The site location is situated at Ologbo Community in Ikpoba Okha L.G.A., Edo State.
The project involves the construction of 35 Nos Bored Casing Piles to 15m depth upon which 2.5 by 45 m long walkway and 10
by 10m jetty platform will be seated upon and surrounded by 400mm reinforced concrete beam on the water side on Oriowon
River in Ologbo.
PROJECT STATUS: Completed – March 2022

Construction/Completion of Concrete Pedestrian Jetty, Ologbo.

BRIEF NOTE: The site location is situated at Irrua, Edo State .
The project involves the construction and placement of surface dressing within the client lodge.
PROJECT STATUS: Completed – March 2022.